Plan consent for qualified person submission
Introduction to plan consent (qualified person submission)

Qualified Person (QP) submissions are submissions made where the applicant is a registered architect or engineer.

To carry out development or renovation works (e.g. new erection, additions & alterations, amendment to approved works) on land and buildings on JTC land, you must obtain JTC's consent for the proposed works. These proposed works must adhere to JTC's and other authorities' regulatory requirements and guidelines. You may also be required to obtain approval from other authorities when relevant. If QP's endorsement is required by the authorities for your project, your submission must be made by a QP.

Submission requirements

Forms

Cover letter

Provide a summary of your proposed development. You can include explanations or information to support your proposal.
Application for assumption of liability form

If the proposal involves an increase in GFA and/ or a change from lower value use to higher value use that exceed the development baseline, for which Land Betterment Charge (LBC), development charge, different premium, levy is payable, the Application for Assumption of Liability form (“Form”) and Letter of Consent (to allow JTC to submit the Form to SLA on behalf of the applicant) shall be submitted together with your proposal to JTC.

Please refer to the drop down ‘Proposals involving land betterment charge’ for more information.

Letter of consent
Authorisation letter from JTC’s tenant/lessee (when the proposed works are not commissioned by JTC’s tenant/lessee) The authorization letter from Lessee/Tenant Company Name shall be:
  • in Lessee/Tenant Company Name's official letter head, addressed to Sub-tenant Company Name;
  • signed by Lessee/Tenant Company Name with the full name and designation of the signatory indicated on the letter;
  • the full project title shall be indicated in the subject title;
  • the content of the letter shall state the following: "We have no objection for the proposed works stated in subject title above and for the submissions to JTC Corporation for the landowner consent and the authorities for approvals.
Self-declaration form The self-declaration form "JTC_LPD_SD.XDFX" can be downloaded from Electronic Submission for Professionals (ESPro)navigate to "Form Templates", select "JTC", select "Plan Consent".
Please keep this form saved in XFDX format.
Letter of declaration for plan consent (SD-LD) form
Letter of declaration for QP to submit for plan consent on the lessee/tenant's behalf. To be stamped and signed by the lessee/tenant.
URA EDA form
To be included only when making Lodgment submissions for
  • Industrial/Warehouse on JTC Land
  • Enterprise District

Download URA’s electronic planning application form EDA form and prepare an EDF file format of the form for submission.
For those submitting the application on behalf of the applicant, prepare a scanned copy of the signed “Authorisation to Submit Development Application” and retain the original letter.
See: Sample Authorisation Letter

Note: Projects that do not require URA’s Planning Permission but still require JTC landowner’s consent should not be lodged (e.g. electrical and M&E works). You will still be required to seek the necessary approvals as required by the relevant authorities.

 URA authorisation to submit development application letter
Clearance from Free Trade Zone Operator (FTZO)  For proposals that involve installation of structures or storage of dangerous goods (DG) at Airport Logistic Park (ALPS). Please email FTZO at enquiry@logparksvc.sg to obtain clearance.
  
Drawings
Proposal drawings to be submitted
  • Computer Aided Design (CAD) or Building Information Modelling (BIM) drawings for your proposed development.
    CAD drawings must comply with the CAD Submission Guidelines.
  • Provide one set of plans consisting of Key/Site Plans, Unit Plan, Sections and Elevations.
  • A Gross Floor Area (GFA) table of the Site Plan showing Site Area, GFA, GFA Quantum Breakdown (e.g. 60:40 split) and Gross Plot Ratio (GPR).
  • To indicate the area of the subject site.
  • To indicate all road names.
  • If the proposed development is Plot Ratio-Exempted, provide a table of the Site Plan showing the proposed site coverage breakdown as depicted in Plot Ratio-Exempted Industries, and also demarcate the corresponding areas.
  • For New Allocation and Lease Renewal cases with A&A/redevelopment works, provide an external perspective, landscape plans and design of boundary walls facing public roads.
  • Submissions involving Space units: Professional engineer’s calculations and drawings, where applicable.

Space submissions

This refers to submissions for units within Multi-User Factory (MUF) developments on JTC land.

 
  • Proposals where JTC’s consent is not required can be found in List A of the Space Submission Handbook. For cases where JTC landowner’s consent is not required, you will be required to seek the necessary approvals as required by the relevant authorities (e.g. SCDF).

  • Please refer to List B of the Space Submission Handbook to determine if QP endorsement is required for the scope of works.
     
  • Please refer to List C of the Space Submission Handbook for buildings with Performance Based Design and List D for Buildings with Green Building Obligations.

For proposals that require fitting out and renovation works, please click here for the process to follow.


Land submissions

This refers to submissions for industrial land, including land with JTC Single-User Factory (SUF), Standard Factory and Terraced Workshop Factory developments.

 

Not all proposals require JTC's consent. For proposals that do not require JTC's consent, please see Annex A and remember to seek the necessary approvals as required by the relevant authorities (e.g. SCDF).

Plan lodgment


The Plan Lodgment Scheme allows the development works to be lodged or registered with URA. It will be considered authorised without further need to apply to URA for planning permission if the works satisfy certain criteria.

Please refer to URA’s Plan Lodgement website on eligibility and lodgement criteria.


Enterprise district lodgment

Submissions within the Enterprise Districts (ED) have a different process. Please click here to see if your proposal falls within the locations of the EDs.

All proposals within the ED should be lodged unless:

  • The submission involves Factory Converted Dormitory (FCD) proposal. Please make a separate submission for the FCD under non-lodgment.

Note: For proposals within the EDs, please pre-consult your Customer Engagement Officer before submitting the proposal to JTC. To find out who your customer engagement officer is, please contact us.

Dormitory

To find out more about conversion to workers' dormitories, please click here.

Please refer to the Guide for Submission involving Dormitory to guide you on the requirements of the dormitory submission.


Diesel and petroleum & flammable material (P&FM) storage / health & safety

Please refer to the Guide for Submission involving Diesel and P&FM Storage to guide you on the requirements of the diesel and P&FM storage submission.


Solar deployment

To find out more about installation of solar photovoltaic (PV) panels, please click here

  • In your submission, please include the autoCAD drawings (.DWG) of the PV and Lightning Protection System (LPS) layout plans.

  • In the drawings, please show the PV elevation and section with details in relation to the building. Please also show the highest existing and proposed platform/floor level (i.e. Singapore Height Datum).

  • PV Layout (to reflect the shape / area of the proposal) should be provided on the Site Plan.

  • On the Site Plan, please reflect the PV Attributes table with the following information:
 Size of solar panel_mm
 Depth of solar panel_mm
 Installation angle _deg
 No. of panels
 PV_Capacity_DC_kWp
 PV_Capacity_AC_kWac
 Total weight_kg
 Area Occupied_sqm
 

Electric vehicles (EV) chargers deployment

If you are keen to deploy EV chargers within your leased/tenanted premises, please consult your JTC Customer Engagement Officer to seek approval for deployment.


Setting out survey requirement for proposed development involving subterranean/airspace/foreshore alienation

If the proposal involves construction of subterranean (e.g. underground passage way) /airspace (e.g. overhead bridge)/foreshore structures (e.g. jetty, wharf, dolphin) outside the allocated land plot, setting out survey plan needs to be submitted. For more information, please refer to Setting out survey requirement for airspace & subterranean alienation and Setting out survey requirement for foreshore alienation.

SLA’s Land Betterment Charge (LBC) Act

  • With effect from 1 August 2022, a new Land Betterment Charge (LBC) has replaced Differential Premium (DP), Development Charge (DC) and Temporary Development Levy (TDL), which were previously administered by the Singapore Land Authority (SLA) and Urban Redevelopment Authority (URA) respectively. The LBC is a tax on the increase in value of land arising from a chargeable consent (e.g. planning permission) given in relation to a development of any land, and is administered by SLA.

  • Under the LBC process, landowners seeking to develop their sites need not make a separate application to SLA for the payment of LBC once a planning application or plan lodgement for an authorised development has been submitted to URA. If a proposed development results in an increase in land value, SLA will follow up directly with the taxable person by issuing a Liability Order (LO) stating the LBC payable. Payment must be made to SLA within 1 month from the date of the LO. This will apply to all planning permissions, plan lodgment and variation of restrictive covenants granted on or after 1 August 2022. 

  • Landowners are the default party liable for LBC. However, for proposals where the increase in value of land arises from their lessees’/ tenants’ or their subtenants’ (“applicant”) proposals, SLA gives landowners the legal option to transfer this liability to the applicant. To effect this transfer, the LBC Act requires the applicant to fill in the Notice of Assumption of Liability Form (“Form”) and thereafter JTC to submit the Form to SLA. Upon SLA’s acknowledgement, SLA will then issue the Liability Order (LO) to the applicant. Following the payment of the LBC to SLA, URA will then issue the planning permission for the applicant to proceed with their proposals.

  • This new process has additional steps of forms-filling to effect the LBC liability onto the correct party, hence may take more time before URA’s Written Permission is released to the applicant (compared to the process pre-1 Aug 22). Hence, to shorten the time that JTC lessees/tenants can get URA’s Written Permission, applicants are encouraged to complete and submit the completed Form as part of your Plan Consent submission via the Corenet, to JTC upfront. Applicants also need to provide a Letter of Consent (as shown below) for JTC to forward the completed Form to SLA. The Letter of Consent will have to be on the applicants’ company letterhead, dated and signed off. This additional paragraph can also be added into the company’s cover letter to JTC for Plan Consent submissions, if you do not want to have a separate letter. When SLA informs JTC about the relevant proposals that incur LBC, JTC will forward the applicants’ completed Form and Letter of Consent to SLA directly. JTC will concurrently alert applicants of the payment, so that applicants can keep a look out for the LO issued by SLA.

I, <Designation> <Name of lessee/tenant>, of <Company’s name> grant consent to JTC to forward the “Notice of Assumption of Liability” form to SLA, in the event LBC is payable arising from the planning application.


  • Please also note that lessees/ tenants will be required to complete and submit a new Form whenever there are changes to the Project Title and for every development proposal of the site. Upon receipt of the LO from SLA, should lessees/ tenants decide not to pay the LBC, the proposal will be considered to be aborted, the earlier-completed Form sent to JTC becomes invalid and URA will not follow up with the issuance of the planning permission.

  • Applicant (lessee/ subtenant/QP) is advised to do a preliminary check if the proposal will result in any land betterment charge payable, via SLA’s online LBC calculator on OneMap  [TBA].

  • For applications submitted by a subtenant of JTC’s main lessee where the proposal results in payment of LBC, the party to pay LBC is a private arrangement to be agreed upon between the subtenant and the main lessee.

    For full detailsplease refer to SLA's website Lease Managements | Singapore Land Authority.